Bond Projects Information

Construction Updates

School Start Open Percent Complete
Valley View Middle School (SHHS Area) Spring 2019 Fall 2020 55%
Maple Grove Middle School (MMHS Area) Spring 2020 Fall 2021 -
Spring Canyon Middle School (SHS Area) Spring 2020 Fall 2021 -
Rebuild Spanish Fork High School Spring 2022 Fall 2024 -
Rebuild Payson High School Spring 2023 Fall 2025 -
Rebuild Springville High School Spring 2024 Fall 2026 -